File #: RES-2024-1411    Version: 1
Type: Resolution Status: Withdrawn
File created: 11/5/2024 In control: Public Works Committee
On agenda: 12/4/2024 Final action: 12/4/2024
Title: RE: Approval of the 1st change order to an agreement between Genesee County and Granger Construction Company, in the amount of $2,500,000.00, for a revised total of $15,668,000.00, to allow for additional construction services in support of the Flint Riverfront Restoration Project; the funding for this amendment will be paid from account 2088-770.32-801.028 and requires no additional appropriation
Attachments: 1. Legistar Submission Checklist_Granger Amendment, 2. AMENDMENT_Granger
To: Ellen Ellenburg, Public Works Committee Chairperson

From: Patrick Linihan, Parks and Recreation Director

title
RE: Approval of the 1st change order to an agreement between Genesee County and Granger Construction Company, in the amount of $2,500,000.00, for a revised total of $15,668,000.00, to allow for additional construction services in support of the Flint Riverfront Restoration Project; the funding for this amendment will be paid from account 2088-770.32-801.028 and requires no additional appropriation

recommendation
BOARD ACTION REQUESTED:
Genesee County Parks and Recreation staff requests the approval of the first change order to the Granger Construction Company contract, increasing the total contract amount to $15,668,000.00, in support of the in-river work of the Flint Riverfront Restoration Project.
BACKGROUND:
ITB #23-354 for the Flint Riverfront Restoration Re-Bid Project was awarded to Granger Construction Company, per RES-2024-233. Granger is providing construction services for all in-river work associated with the Flint Riverfront Restoration project.
DISCUSSION:
Progressing, additional services items have been identified, requesting a change order to the total contract amount from $13,168,000.00 to $15,668,000.00, a $2,500,000.00 increase.

Riffle #4 of the in-river project has presented greater thickness of the Hamilton Dam than expected and more scouring downstream than expected, requiring additional construction services, including construction causeway, dam demolition, excavation and disposal, and fill riffle material.
IMPACT ON HUMAN RESOURCES:
None.
IMPACT ON BUDGET:
NO USE OF GENERAL FUND. NO USE OF PARKS FUND.
To be paid from account 2088-770.32-801.028.
IMPACT ON FACILITIES:
None.
IMPACT ON TECHNOLOGY:
None.
CONFORMITY TO COUNTY PRIORITIES:
This request directly supports the promotion of environmental stewardship, promotion of public health, and promotion of safe communities, creating economic growth in the area.













...