Skip to main content
Genesee County Logo
File #: RES-2025-1957    Version: 1
Type: Resolution Status: Passed
File created: 7/1/2025 In control: Board of County Commissioners
On agenda: 8/20/2025 Final action: 8/20/2025
Title: RE: Approval of an agreement between Genesee County and MIHM Enterprises, in an amount not to exceed $392,486.00, to provide for repairs to the Richfield County Park Historic Foot Bridge; the cost of this agreement will be paid from account 2088-770.35-974.000
Attachments: 1. Legistar Submission Checklist_Historic Foot Bridge, 2. BIDS_FOOT BRIDGE, 3. CC_MIHM Enterprises_ Richfield Bridge Exterior Repairs, 4. COI_MIHM
To: Brian K. Flewelling, Public Works Committee Chairperson

From: Patrick Linihan, Parks and Recreation Director

title
RE: Approval of an agreement between Genesee County and MIHM Enterprises, in an amount not to exceed $392,486.00, to provide for repairs to the Richfield County Park Historic Foot Bridge; the cost of this agreement will be paid from account 2088-770.35-974.000

recommendation
BOARD ACTION REQUESTED:
Genesee County Parks and Recreation staff requests the approval to award ITB #25-448 - Exterior Repairs: Richfield County Parks Historic Foot Bridge to MIHM Enterprises, for a total amount not to exceed $392,486.00.
BACKGROUND:
In support of restoration and preservation efforts of historical structures, Parks had a study completed in 2022 of Parks historical structures, their current condition, and recommended action. The Department is seeking fund sources to prioritize and complete recommended actions on these structures. The Richfield County Park Historic Foot Bridge is a prominent feature of the park, hosting many weddings, ceremonies, and photography sessions, as well as provides connection to the north and south portions of the park, crossing the Flint River. For these reasons, the historic foot bridge is a top priority in preservation and renovation efforts.

The Invitation to Bid was advertised by the Genesee County Purchasing Department. Proposals were received until May 16, 2025. Three bids were received. Proposals were reviewed by Parks Director, Park Superintendent, Parks Operations Manager, and MacMillan Associates, who are providing engineering and construction management services for the project, per RES-2024-659.
DISCUSSION:
MIHM Enterprises has significant experience with renovation of historical structures, including WPA and CCC historical structures in partnership with the State of Michigan. Staff is confident in their ability to successfully complete exterior repairs to the foot bridge. MIHM was also the lowed bid submitte...